Carbon capture, utilization and storage

Opportunity
Specific Challenge

Enabling cross-border transportation and sequestration of industrial CO2

REGION REGION

Norway

REGION

Challenge

  • Completing the first two wells for a commercial CCS project in the North Sea, which can store 1.5 million metric tons of liquid CO2 annually 
  • Delivering safe and cost-efficient wells for permanent CO2 sequestration with a focus on well integrity

Solution

  • XtremeGrip® low ECD and Quick Lock liner hangers 
  • Versa-Trieve® packer 
  • X-Trieve™ XHHC retrievable production packer 
  • FS2 fluid loss control valve 
  • Hydrostatic-set Perma-Series® HNT packer 
  • Opsis® gauges 
  • NeoStar™ tubing-retrievable safety valve (TRSV)

Result

  • Successfully delivered full well completion solution for open-source offshore commercial cross-border CO2 transport and storage facility 
  • Delivered two wells using completion technology that enabled the safe and controlled conveyance of CO2 from surface to geological formation for sequestration

Overview

Halliburton successfully delivered a top-to-bottom completion solution for a cross-border CO2 transport and storage facility. Phase I of this project includes the capacity to transport, inject, and permanently store up to 1.5 million metric tons of CO2 per year. CO2 storage will be possible through one injection well, which was sidetracked and completed from the original exploration well and a new contingency well. With these two wells in place, the customer is motivated to drill and complete three additional injection wells to expand capacity by an additional 3.5 million metric tons to a total of 5 million metric tons annually. The expanded capacity will help the customer accelerate industrial decarbonization and provide future CO2 storage options for Europe.

Challenge

The safe and successful design and operation of carbon capture and storage (CCS) wells requires careful consideration of a range of technical challenges. The primary objective is to ensure the permanent sequestration of CO2 underground, which is dependent on the integrity of the well. One challenge is helping prevent leakage of CO2 to the atmosphere, which could occur if materials used during well construction are not selected carefully. For example, the formation of carbonic acid (H2 CO3 ) due to the mixing of dry CO2 and saline formation water can lead to corrosion of carbon steel, potentially having negative impact on well integrity. To help prevent such issues, operators must select materials suitable for the well environment and compatible with the operator’s objectives.

Solution

To help ensure the safe and permanent storage of CO2 during well construction, several factors were considered, including injection CO2 composition, anticipated reservoir pressure evolution, well temperature variations during injection and shut-in, formation fluids composition, and previous knowledge gained from other CO2 injector wells. Laboratory corrosion testing determined that tubulars and completion equipment installed at the bottom of the well should be 25% chrome alloy or superior materials to allow a 25-year well lifetime.

During well construction of the primary injection well, a 14-inch XtremeGrip® low equivalent circulating density (ECD) and 9 5/8-inch XtremeGrip Quick Lock liner hanger were installed and sand control was achieved using standalone sand screens (SAS) in the openhole section. For the lower completion of the well, the Halliburton Versa-Trieve® retrievable sand control packer and FS2 fluid loss control valve were used. The upper completion was finalized using the Halliburton hydrostatic-set Perma-Series® HNT packer, 4 1/2- and 7-inch Opsis® gauges and the NeoStar™ TRSV  to ensure safety.

The contingency injector was completed in a similar manner. A 14-inch Low ECD liner hanger was installed during well construction and sand control was achieved by gravel packing the openhole section. A Versa-Trieve retrievable sand control packer and FS2 fluid loss control valve were used for the lower completion, and the upper completion consisted of the X-Trieve™ XHHC retrievable production packer, two 7-inch Opsis gauges and the NeoStar TRSV.

 

icon

CCUS

First open-source opportunity for customer

Well completion solution creates first open-source opportunity for customer to provide safe and successful industrial transport, storage and decarbonization as a commercial service.

Results

Halliburton delivered a full well completion solution for the open-source offshore commercial cross-border CO2 transport and storage demonstration project, which will accelerate industrial decarbonization and provide future CO2 storage options for Europe. 

Once Phase I of the project is completed, the operator will have the capacity to capture and store 1.5 million metric tons of liquid CO2 annually. Based on customer demand, the operator can drill and complete additional wells to increase the storage volume annually.

Related products

Intelligent Completions

Intelligent Completions

Halliburton SmartWell completion systems allow you to collect, transmit, and analyze completion, production, and reservoir data while also controlling and monitoring selected reservoir zones remotely and in real-time.

Explore
icon

READY TO TAKE THE NEXT STEP?

Talk with a Halliburton completion tools expert

get in touch