Specific Challenge

Improve well placement in uncertain reservoir conditions and downhole challenges

Region - Offshore Malaysia Region - Offshore Malaysia

Malaysia

Region - Offshore Malaysia

Challenge

  • Optimize horizontal well placement in uncertain reservoir conditions 
  • Drill reservoir section in one run with downhole challenges
  • High torque and drag, hole cleaning, and ECD limitations
  • Vibration challenges with a 250-ft borehole assembly (BHA)

Solution

  • Use of Geo-Pilot® 7600 RSS, M/LWD sensors, and GeoTap® formation pressure testing service for precise wellbore placement and accurate real-time pore pressure measurements
  • Use of EarthStar® geosteering to enable modeling and analysis of logging while drilling (LWD) data for quick decision-making

Result

  • Saved five rig days for the operator 
  • Reached optimal landing point, aided by reservoir insight and engineered drilling solution

Overview

After a successful offshore development campaign, an operator in Malaysia asked Halliburton to develop a geosteering solution for an extended reach drilling (ERD) well. The goal was to maximize reservoir contact and enhance understanding for future development. Halliburton’s multidisciplinary team collaborated with the operator and third parties to address challenges, such as stratigraphic changes and potential reservoir exits. The team used advanced tools such as Geo-Pilot® 7600 rotary steerable system (RSS) and GeoTap® formation pressure testing service to drill, geosteer, and log the well in one run.

This integrated approach saved five rig days and improved reservoir insights.

Challenge

The operator encountered challenges drilling an ERD well with the longest shallow true vertical depth (TVD) in the area. Key obstacles included the navigation of stratigraphic lateral changes and the risk of reservoir exits in the horizontal section. The operation required precise geosteering, logging, and well placement within the reservoir’s sweet spot. Additional risks involved anticollision, high torque and drag, hole cleaning, equivalent circulating density (ECD) limitations, drilling into depleted zones, and vibration issues with a 250-ft borehole assembly (BHA). This was the operator’s first attempt to drill, geosteer, and log the reservoir section in a single run — a factor that added complexity and potential risks to the project.

Solution

Halliburton collaborated with the operator to design a comprehensive solution to optimize drilling performance and mitigate potential risks. Key technologies included the Geo-Pilot® 7600 RSS, a full suite of measurement-while-drilling sensors, and the GeoTap® formation pressure testing service. An automated vibration dampening system was critical in the reduction of stick-slip and torque fluctuations. This mitigation helped enable superior drilling performance. The Geo-Pilot® system facilitated a smooth wellbore, while GeoTap® provided real-time pore pressure measurements with high accuracy.

The project management team used multiwell data analytics and performance benchmark tools to evaluate historical offset wells, identify visible lost time, and define areas for improvement. Customized drilling and tripping practices and optimized solids-control equipment enhanced hole cleaning efficiency.

Building on these insights, Halliburton’s integrated remote operations team optimized drilling and tripping parameters. LOGIX™ automation and remote operations improved time calculations and projections.

This integrated approach enabled the operator to drill the reservoir section in one run. This efficiency saved five rig days and improved reservoir insights.

Receiving recognition from the operator and regulator is a testament to the successful multidisciplinary approach.

Shaun Able, account vice president, Halliburton

Result

Halliburton’s customized solutions helped the operator achieve efficiency and maximize reservoir contact. With the placement of the well in the sweet spot and extension of the lateral section, the operator maximized reservoir contact and enhanced gas production. The customized bottom hole assembly (BHA) allowed the operator to complete operations in a single run. This saved time and reduced costs.

Halliburton’s integrated approach enabled the operator to drill the reservoir section in one run for the first time. This saved five rig days and improved reservoir insights. The success not only optimized current production but provided a solid foundation for future development and appraisal efforts.

Explore our portfolio

Integrated Well Construction

Integrated Well Construction

Halliburton collaborates with all stakeholders to develop a robust design and an effective program tailored for each well construction project.

Explore
Automation and remote operations

Automation and remote operations

Increase the consistency and performance of well construction operations by integrating subsurface automation, digital twins, and remote operations.

Explore
Geo-Pilot® rotary steerable system

Geo-Pilot® rotary steerable system

The Halliburton Geo-Pilot® rotary steerable systems (RSS) is designed to deliver unprecedented speed and precise steering.

Explore
icon

Ready to take the next step?

Talk with a Halliburton project management expert

Get in touch