BridgeBlend™ lost circulation material cures losses and reduces rig time
Download PDFMature Fields
Severe to total lost circulation in karstified dolomite formation
Iraq
Characterized by the karstified dolomite of the Dammam formation, an oil field in southern Iraq presents a unique set of lost-circulation challenges. Operators and service companies have exhausted options for more than a decade to address losses in this region.
Drilling through karst facies at depths from 450 to 650 m poses a formidable challenge. Up to 90% of wells experience severe to total lost circulation attributed to geological characteristics, such as caverns, vugs, and large fractures. The Dammam formation consists of interbedded limestone and dolomite with karst that ranges up to large-scale cave/void systems. These large voids lead to lost circulation and complicate operations, which increases rig time and costs. Operators have historically used conventional lost circulation materials (LCMs), thixotropic cement systems, and multiple cement plugs, but with limited success.
Halliburton worked with the operator to develop a solution to address losses using BridgeBlend lost circulation material (LCM), which is comprised of a blend of fibers, resilient angular particles, and coarse materials. Rigorous engineering, which included computer-aided simulation and laboratory testing, helped determine the optimal concentration of BridgeBlend LCM to effectively pump through the drill pipe. Before field deployment, thorough tests and verification helped ensure ease of mixability at the surface.
An optimal concentration of 29 lb/bbl of BridgeBlend LCM was used to address and block voids in the Dammam and reinforce the formation. The solution was batch mixed into the cement slurry and pumped through open-ended drillpipe.
lb/bbl of BridgeBlend LCM used to address voids
Lost-circulation plug cured losses
Losses after solution was deployed
BridgeBlend LCM enabled drilling and primary cementing operations to proceed without losses. This tailored lost-circulation solution cured losses with a single lost circulation plug, a result that outperformed the usual four to six conventional cement plugs required per well. The operator saved significant rig time and costs per well compared to the conventional approach. BridgeBlend LCM is now the operator’s preferred solution to cure losses in the area.