Deep Water

Opportunity
Specific Challenge

Lower completion installed in deepwater well

REGIOn REGIOn

Brazil

REGIOn

Challenges

  • Lower completion installed in deepwater well
  • Delayed delivery of upper completion equipment
  • Temporarily suspend well using V0-qualified retrievable bridge plug

Solution

  • The API 11D1 V0-qualified Intercept® retrievable bridge plug met all operator requirements for temporary well suspension

Results

  • Deployed and installed the Intercept retrievable bridge plug for 780 days until successful retrieval
  • Upper completion equipment delay led to significantly longer than expected temporary abandonment
  • Longest temporary abandonment using the Intercept retrievable bridge plug to date

Overview

Faced with upper completion delivery delays, the operator of a deepwater well in Brazil required a temporary abandonment solution to isolate the lower completion. Halliburton recommended the Intercept® retrievable bridge plug to provide the necessary well suspension barrier until the upper completion equipment arrived onsite.

Challenge

After lower completion installation, a deepwater well drilled to a depth of approximately 6,000 ft (1,829 m) necessitated temporary abandonment while waiting for the upper completion equipment to arrive. Safe suspension required an API 11D1 V0-rated retrievable bridge plug to provide a temporary barrier. However, the tool was not intended to remain in the well for an extended period.

Solutions

Halliburton provided a 10 3/4-in. Intercept retrievable bridge plug, which met the operator requirement for a reliable API 11D1 V0-rated barrier. A Halliburton service specialist set the plug at approximately 7,300 ft (2,225 m) at an inclination of approximately 22 degrees, with minimal hang weight below, and successfully pressure tested the tool to 5,500 psi. 

780

days the RBP provided a barrier

7,300

ft, plug was set depth

5,500

psi - successfully pressure tested

Results

The Intercept retrievable bridge plug provided a mechanical isolation solution for 780 days. Halliburton successfully retrieved the tool upon the arrival of the upper completion equipment. This record-setting well suspension demonstrates that the Intercept retrievable bridge plug offers a reliable, gas-tight barrier for both short and long-term temporary abandonment operations.

Retrievable Bridge Plugs

Gas-tight, well-suspension barrier technology without the hang-weight

Halliburton Intercept RBP is a gas-tight, well-suspension plug ideal for dual-barrier applications and is designed to handle a wide range of well conditions.

Download Data Sheet
Intercept retrievable bridge plug
Intercept retrievable bridge plug

Related products

Well Suspension Tools

Well Suspension Tools

Enable a wide range of well support operations, save time, and reduce risk with Halliburton retrievable well suspension tools.

Explore
icon

READY TO TAKE THE NEXT STEP?

Talk with a Halliburton completion tools expert

Get in touch