Search
Opportunity

Deepwater

Opportunity
Specific challenge

Reduce operational time to abandon target zone

Region

West Africa

Region

Challenge

  • Reduce operational time to abandon target zone, which averages eight days

Solution

  • Incorporate BHKA™ tool into well abandonment design to simplify cement operations and reduce TCO

Result

  • Reduced rig time by 132 hours and saved approximately USD 2.3 million
  • Operator plans to incorporate BHKA™ disconnect tool into P&A toolbox for four subsequent wells, which could save up to USD 13 million

Overview

To improve drilling performance, significant resources are dedicated to well design, directional services, bit selection, drilling fluid, etc. However, operators can achieve significant rig time savings by simplifying temporary or permanent abandonment programs in exploratory or development wells. 

Challenge

A major operator with shelf and deepwater assets in Sub-Saharan West Africa plans several exploratory and development wells, which require temporary and permanent abandonment programs under various conditions. The operator’s standard operational procedures require isolation of each hydrocarbon-bearing zone via conventional cement plug placement with verification after waiting on cement (WOC). 

In a previous exploratory well, the operator’s final abandonment program required the placement of five stacked cement plugs to isolate each target zone. The program was executed successfully over eight days but incurred USD 3.1 million in overall costs associated with rig time.

Solution

To reduce the total cost of ownership (TCO), Halliburton recommended incorporating the BHKA™ plug setting disconnect tool to simplify cement plug setting procedures. This tool replaces consecutive stacked plugs with a single, longer cement plug. The BHKA plug setting disconnect tool facilitates unlimited cement plug length through safe disconnection of the work string from the tail pipe, which reduces the risk of a stuck string and eliminates the need for multiple plugs and WOC in between plugs.

2

Trial operations

130

Hours rig time saved

2.3

Million USD saved

4

Future wells planned

Result

The operator agreed to deploy the BHKA™ tool for a trial operation to analyze the results and evaluate its application in future wells. Halliburton tailored the operational design for two applications as a proof of concept.

The first application, designed to permanently abandon the 12 1/4-in. pilot hole of a deepwater producer well, consisted of a 5-in. outside diameter BHKA tool with 400 m of 4 1/2-in. sacrificial tail pipe, run in hole with a 5 7/8 × 3 1/2-in. combined drillpipe work string. The operation was executed in adherence to the cement program. Halliburton deployed an MCXV releasing dart from the Commander™ 1000 cement head and displaced it to land and operate the single-collet release mechanism at a differential pressure of 2,600 psi. The tail pipe released, achieving planned coverage above the target zones in the pilot hole.

The next deployment was in an exploratory well, where the solution was designed to replace two subsequent 200-m-long cement plugs with a single cement operation to achieve the required isolation. Similar tubulars and the BHKA tool were used. The cement operation proceeded as planned and was completed with the release of the sacrificial tail pipe and differential pressure of 2,200 psi applied on the landed dart. The objective to provide 100 m of isolation above the target zone was achieved on the first attempt.

The successful proof of concept demonstrated the tool's reliability to the operator, familiarized them with tool procedures, and confirmed potential savings if implemented in future wells.

Modifying the abandonment strategy to permanently isolate the pilot hole resulted in an estimated savings of USD 2.3 million and 132 hours of rig time. The operator now plans to use the BHKA tool in four additional wells in the region,  potentially saving up to USD 13 million.

Featured products

BHKA™ plug setting disconect tool

BHKA™ plug setting disconect tool

The Halliburton BHKA™ plug setting disconnect tool simplifies cement plug placement when necessary during well construction or abandonment operations.

Explore
Commander™ 1000 top-drive cement head

Commander™ 1000 top-drive cement head

Designed for offshore operations to surface launch balls or darts in order to operate subsea plug sets and associated tools.

Explore
icon

Ready to take the next step?

Talk with a Halliburton cementing expert

Get in touch