Opportunity

Mature Fields

Opportunity
Specific challenge

Remove milling debris under sustained pressure and maintain safe operations

Middle East

Middle East

Middle East

Challenge

  • Execute multi-stage fracking operations
  • Mill and clean out perforating plugs between stages
  • Remove milling debris under sustained pressure 
  • Control fluid loss

Solution

  • Bullhead 150-pcf OBM to kill well during coiled tubing operation 
  • Deploy GDVU with 125-mm annular cutter to mill plugs to 3 1/8-in. depth 
  • Use constant circulation system to flow kill-weight mud and monitor fluid loss 
  • Remove debris using a compressed air jetting tool

Result

  • Maintained zero psi wellhead pressure with periodic OBM application
  • Milled plugs to target depth between fracturing stages 
  • Recovered BPV coupon and removed debris safely
  • Enabled uninterrupted multi-stage fracturing

Overview

An operator in the Middle East achieved uninterrupted multi-stage fracturing by collaborating with Halliburton Boots & Coots® to implement a tailored well control solution. After drilling and completing a horizontal gas producer well, the operator performed a 46-stage hydraulic fracturing operation and installed a 5-in. Cameron Type H back-pressure valve (BPV) for well control. Each stage required milling perforating plugs, but high wellbore pressure and exposed upper perforations caused repeated BPV removal failures. The challenge threatened operational continuity and increased risk for personnel and equipment.

Challenge

Operations in the Middle East often involve gas extraction from high-pressure, tight reservoir rock. During this campaign, the operator faced 2,000 psi of wellbore pressure beneath a 5-in. Cameron Type H BPV after bullhead injection of 111 pfc (14.7 ppg) brine. The operator struggled to retrieve the BPV before deploying coiled tubing to mill the plugs. Persistent well pressure also restricted debris removal and raised concerns about maintaining safe conditions for milling operations. 

Solution

Halliburton Boots & Coots® proposed a customized well control strategy tailored to the well’s conditions. The plan called for bullhead injection of 150-pcf oil-based mud (OBM) into the 5½-in. production casing with a constant circulation system to distribute kill-weight mud evenly across the wellhead. This approach helped keep the well full of kill fluid and facilitated real-time monitoring of fluid loss rates.

To remove the BPV, the team deployed a 125-mm annular cutter mounted on the gate valve drilling unit (GVDU). The process was designed to maintain a maximum loss rate of 3 bbl/hr for safety. The team killed the well by bullheading a total of 350 bbls of 150 pcf OBM to overcome the recorded bullhead pressure of 3,400 psi. When the loss rate exceeded 3 bbl/hr. threshold, personnel monitored the well for two hours and pumped additional kill mud until the pressure stabilized at 0 psi. To keep the well dead, the team bullheaded 10 bbls of 150 pcf OBM every three hours.

To operate the GDVU safely from the work platform, the team removed one wellhead valve to lower the tree top. This step was approved through the management of change process, and two mechanical barrier policies remained in place throughout milling. Compressed air jetting was selected for debris removal, and the BPV coupon was recovered with a retrieval tool on a dry rod.

Result

Halliburton’s solution allowed the operator to mill perforating plugs to a target depth of 3 in. using three 125-mm annular cutters. Bullhead injection of OBM and constant circulation methods provided effective well control and allowed accurate monitoring throughout the operation. The operator reported satisfaction with the incident-free outcome. This operation enabled uninterrupted multi-stage fracturing and protected onsite personnel, equipment, and the environment.

Related products

Gate valve drilling

Gate valve drilling

Restore well integrity by enlarging gate valves or ball valves that have become inoperable.

Explore
Well control remediation

Well control remediation

Implementing tailored solutions to regain control and return well integrity.