Fayetteville, Arkansas: Continuous Real Time Fluids Measurements Leads to Rig Site Problem Solving
Drilling an intermediate section of the Fayetteville shale play, an operator was looking to increase the amount of fluids data present so they could make better decisions concerning their operations.
|
|
|
Egypt: HYDRO-GUARD® water-based drilling fluid system replaced competitor silicate mud, delivering stable wellbore through troublesome shale
Baroid recommended HYDRO-GUARD water-based
drilling fluid system along with the addition of BAROTROL
PLUS additive to provide optimum inhibition in the
troublesome shale.
|
|
|
Fayetteville, Arkansas: SHALEDRIL™ F Water-Based Fluid Proves Successful on Troublesome Fayetteville Shale
The Marrowian shale that
lies above the Fayetteville Shale in Arkansas is highly reactive
and prone to fracturing and delamination. It is typically drilled
with an Invert Emulsion fluid, which redu
|
|
|
Gulf of Mexico: GEM™ Water-Based Drilling Fluid Combats Highly Reactive Shales
GEM™ Water-Based Drilling Fluid Combats Highly Reactive Shales, Provides Near Gauge Wellbore
|
|
|
Expedite® Service Prevents Proppant Flowback; Saves Operator $14,400 (Case History)
An operator wanted to prevent proppant from flowing back after fracturing a 3000 foot horizontal lateral in a Devonian formation. Previously the lateral had been treated with acid soluble cement and
|
|
|
Barnett Shale: Highly Inhibitive SHALEDRIL™ Water-based Mud System Results in Zero Liquid Mud Haul Off and Saves Operator Approximately $750,000
A major operator in the Barnett Shale was looking to drill extremely challenging wells while controlling costs.
|
|
|
Advanced Stimulation Techniques Add Almost $227,000 in Production (Case History)
Calculations indicated that available reserves in a 9,500 foot well in a Cotton Valley formation were not being recovered by existing production. The operator was also concerned that he could end up l
|
|
|
Field Record –Footage Drilled Cotton Valley Application Lowest Interval CPF
The 9 7/8”FMHX853ZZ drilled 3,133 feet at a ROP of 22.3 ft/hr. The FMHX853ZZ eliminated a minimum of one bit run for interval drilled and provided the lowest interval CPF –more than $15.00/foot lower
|
|
|
Drilled Curve and Lateral Outstanding Footage Excellent Overall ROP
The 6 1/8”FMX731Zdrilled 4,808 feet at a ROP of 28.4 ft/hr. The FMX731Z drilled the “Curve”and “Lateral”intervals of this Haynesville Shale application in one bit run –an interval normally requiring t
|
|
|
Drilled Entire “Curve Radius” and “Lateral” Intervals
The 6 ¾”FMX731Zdrilled 5,269 feet from 10,802’MD to 16,071’MD at an overall ROP of 23.3 ft/hr. The FMHX731Z drilled the entire“curve radius”and the “lateral’intervals in one run building hole angle fr
|
|
|
Expedite Case Histories Magazine Supplement
This case history was presented in the magazine supplement published in E&P and Oil and Gas Investor 2005.
|
|
|
Enhancer 923 agent blended into cement slurry overcomes annular gas migration issues in the Barnett Shale
An operator in the Barnett Shale asked Halliburton to help mitigate annular gas migration while enhancing wellbore
stability for zonal isolation integrity throughout the life of their wells.
|
|
|
Devonian Stimulation Increases Value by Approximately $2.75 Million (Case History)
An operator needed to provide adequate stimulation for a 12,000 foot well in a Devonian formation with open Strawn perforations above the completion packer.
|
|
|
Geo-Pilot® Dirigo System Helps Shave Five Days from Plan, Drilling Long Horizontal Section in One Run
The operator drilling a shale oil well in Argentina wanted to reduce operating time and associated costs while drilling both the build and horizontal sections in an 8-1/2 inch hole size.
|
Mar 2013
|
|
Halliburton helped assess resource potential and optimize investment decision-making in shale plays
Asset evaluation and risk assessment of unconventional fields
|
Dec 2012
|
|
LaserStrat® In-Field Service Helps Deliver Vastly Higher
Obtain detailed reservoir information for optimum hydraulic fracturing along the lateral to improve the percentage of fractured intervals.
|
Jul 2012
|
|
GeoForce® XL Motor Powers Through Three Forks Resource Play
The operator enlisted Halliburton to drill almost 10,000 feet (2,956 meters) laterally in one of the prime U.S. unconventional oil plays, the Williston Basin.
|
Jun 2012
|
|
Sperry Drilling’s New Data Compression Software Facilitates Geosteering Within Thin Reservoir while Significantly Reducing Drilling Time
In this shale gas well in the Eagle Ford play in Mexico, the primary objective was to drill a horizontal well with maximum lateral exposure within the 10 feet (3 meters) thick production zone. The cha
|
Jun 2012
|
|
Sperry Combines ALD™ and DGR™ Sensor Data for Innovative Solution in Difficult GOM Deepwater Well
In this deepwater well in the Gulf of Mexico, the customer began experiencing problems with the borehole after successfully drilling to the conventional core point of the main reservoir.
|
May 2012
|
|
EZ-Pilot® System Helps Deliver Shale Gas Well Four Days Early
The operator needed to drill the well with a rotary steerable system and did not want to compromise on service quality, but the proposals they received were far above the budget of a conventional shal
|
Apr 2012
|